Time and Work Aptitude Questions with Solutions Quantitative Aptitude Basic Sample Problems

Time and Work Aptitude Questions with Solutions Quantitative Aptitude Basic Sample Problems


Time and Work Problems Tricks & Shortcuts: Time and Work Aptitude Questions are comes under the category of the Quantitative Aptitude. This is one of the easiest Aptitude Question asked in the many competitive exams such as bank exam, CAT, UPSC exam, IBPS, SSC etc.., You can easily get the full marks easily in the Time and Work Questions. If you want to tackle the time and work question asked under the Quantitative Aptitude, You should follow the basic concept, Tips, Tricks & shortcuts. We will provide some simple and sample example asked frequently in the competitive exams like bank exam, CAT, UPSC, IBPS Exam, SSC etc.., These Time and Work Aptitude Questions with Solutions will surely helps you to crack the competitive exams.

Time and Work Example Problems:-


Q1: Prabu can do a work in 10 days, Muthu can do it in 12 days and Karthic can do it in 15 days, In how many days they finish the work, working together?

(a) 4
(b) 5
(c) 6
(d) 7

Q2: (x - 2) women can do a job in x days and (x + 7) women can do 74% of job in (x - 10) days. Then, in how many days can (x + 10) women complete the job?

(a) 23
(b) 12
(c) 25
(d) 17

Q3: Srinath can do a work in 14 days, while Ram can do it in 21 days. In how many days, working together they will finish the whole work?

(a) 8.4
(b) 9
(c) 8.5
(d) 10

Q4: If 20 men can do a work in 7 days, then calculate the number of persons required to complete the work in 28 days? 

(a) 20
(b) 15
(c) 10
(d) 5

Q5: Pipe A can fill a tank in 10 hours and pipe B can fill it in 15 hours. Both are flowing simultaneously. Later pipe B was closed, then it takes 8 hours to fill up the whole tank. After how much pipe B was closed?

(a) 3
(b) 4
(c) 5
(d) 6

Q6: IF 10 men can do a work in 20 days, then 20 men with twice the efficiency can do the same work in?

(a) 10
(b) 5
(c) 30
(d) 35

Q7: Man A is twice as good a man B and therefore Man A takes 6 days less than Man B to finish the work individually. If Man A and man B working together to finish the work in 4 days, then how many days are required by Man B to finish the work alone?

(a) 14
(b) 12
(c) 16
(d) 18

Q8: Tap A & B can fill a tank in 10 hours & 5 hours respectively. When third tap C, which works as an outlet tap is also open, then the tank can be filled in 18 hours. The outlet tap can empty a full tank in?

(a) 9 hours
(b) 8 hours
(c) 5 hours
(d) 7 hours

Q9: 4 men & 4 women can do a job in 10 days, 6 men & 6 women can do the same work in 7 days. In how many days can 2 men & 7 women finish the same job, working together?

(a) 10
(b) 12
(c) 14
(d) 8

Q10: 16 boys completed one-third job in 6 days. The number of additional men are requires to finish the work in next 6 days.

(a) 15
(b) 40
(c) 20
(d) 16

Time and Work Aptitude Questions




Answers:-


Q1: (a) 
Q2: (b) 
Q3: (a) 
Q4: (d)
Q5: (a)
Q6: (b)
Q7: (b)
Q8: (a)
Q9: (c)
Q10:(d)